The builders and plasterers were very busy today finalising most of the remaining items for the fix. Lots and lots of progress today:
- All skirts and architraves have been installed
- Shelving in all the cupboards and the master walk in robe are done (just waiting on the materials to finalise bedrooms 2 and 3)
- Flue has been installed in the chimney
- Extra ceiling panels have been installed in the family room, hallway, bedroom 2 and bedroom 3
- Fretwork has been installed in the hallway
- Doors and handles have been installed
The fix should be completely finalised in the next few days, then we should see the painters, the tilers, and the electrician move in.
Lots of pictures of all the work today:
Theatre architraves |
Theatre room with the doors closed |
Architraves and skirting installed in the dining room |
Skirting highlights in the kitchen |
I like how they have carried the skirt around the fridge space, and have neatly cut out the water point |
Linen cupboard fitted out |
Left side of the walk in robe - oh the shoes I can store up on those shelves...can't wait! |
Back of the walk in robe |
Right side of walk in robe |
Cabinet in the family room |
Pantry shelving |
Close up of the door handles (and a smudgy door) |
Bullnose window sill over the kitchen sink |
Another bullnose sill around the window seat |
Holes in the ceiling ready for the ceiling rose to be installed |
Pressing it into place |
Done! |
Ceiling rose in the hallway |
Hallway fretwork |
Front shot after a bit more of a site clean up |